Civil Construction Updates |
February 2008 |
Daya Bay started blasting on Feb. 19, 2008.
The access tunnel portal. The reinforcement of the portal is done. The tunnel has been excavated for ~10 meters.
|
Closer view of the access tunnel portal. The worker is applying shotcrete.
|
Portal of the construction tunnel. Workers are drilling.
|
Portal of the construction tunnel. Workers are burying explosive after drilling.
|
Portal of the construction tunnel after blasting. The framework around is construced against fly rock. |
|