Civil Construction Updates
 

March 2008

The Surface Assembly Building (SAB) starts construction on Mar. 15, 2008

Up to Mar. 15, 2008, Access tunnel was excavated 12 m, Construction tunnel was excavated 24 m.

1) The Access Tunnel

The open arch of the access tunnel portal.

 

The open arch of the access tunnel portal.

 

The open arch of the access tunnel portal.

 

The access tunnel portal

 

Fly rock shed at the access tunnel portal.

Inside the access tunnel portal

 

 

2) The Construction Tunnel

 

3) The Surface Assembly Building

 The Surface Assembly Building

 

The Surface Assembly Building

 

Excavation of the Pile foundation

 

Static blasting of the isolated rock in the pile foundation

 

Ground water in the excavated pile foundation